runway

St. George Airport runway 90% complete
Day 101 of The Runway Project and it's 90% complete! The project site continues to be a busy place with efforts focusing on removing dirt and debris from the runway and any rocks larger than three inches from the airfield, finishing runway light cans, sign pads and junction plazas, installing fencing, and grading all of the infields disturbed by construction and along the new pavement...
St. George Airport runway now 80% complete
As of today, the project is 80% finished with all asphalt paving completed! Crews placed 27,600 tons or 55,200,000 pounds of asphalt in the reconstructed 5,400-foot section of runway and along the runway shoulders. Finishing the asphalt paving is a huge milestone for the project...