SG Airport runway reconstruction making good progress
SG Airport runway reconstruction making good progress
SG Airport runway reconstruction making good progress
The St. George Airport runway reconstruction project hit the 30% completion milestone. About 2,800 feet of the critical reconditioned clay plug material was placed. There is another 2,600 feet of this material to install. Crews continue to work two, 11 hour shifts per day, five days a week including July 4th...
St. George Airport to close tonight
The St. George airport serves more than 200,000 commercial passengers a year. The airport will close for four months to let crews rip up and rebuild a runway undermined by unstable blue clay. St. George Regional Airport manager Rich Stehmeier talking with Andy on the Andy Griffin show calls the $25 ...